Construction of the new Beijing airport is behind schedule

Date: 13:18, 11-12-2015.

Almaty. December 11. Silkroadnews - Construction of a new Beijing airport is behind schedule due to delays in land requisition and demolition of houses to the resettlement of local people, reported Chinese media.
According to the National Audit Office of China, by the end of October in Beijing and the province. Hebei plot was transferred less than half the required area. For the construction of the airport is required 16.7 million square meters of land of the planned 27.3 million square meters.
Construction of the new Beijing airport, which was authorized by the State Council in December 2012 is considered a key step for the coordinated development of the region, the Beijing-Tianjin-Hebei, and is expected to be completed by 2019.
Meanwhile, the schedule also lags behind the construction of a number of other large projects, particularly in the construction of 12 railway facilities, invested nearly 10% of the planned annual investments which had to reach 8.57 billion yuan ($1.33 billion).

Share the news: