Deputy Prime Minister of Tajikistan is dissatisfied with the pace of work on the railway Vahdat-Yavan

Date: 13:23, 18-06-2015.

Almaty. June 18. Silkroadnews - "Vice Prime Minister of Tajikistan Azim Ibrokhim acquainted with the construction of tunnels on the railway section Vahdat-Yavan and expressed dissatisfaction with the pace of work on this railway", - reported the TajikTA.
In particular, he instructed the responsible leadership to strengthen the pace of construction work as much as possible and to improve the quality.
Currently, on the railway sector Vahdat-Yavan built 3 tunnels. First (length 2.68 km) erected from two directions; the second (680 meters) - at one; third (735 m) - is in the process of preparatory work.

Share the news: